Tower-A
- Structure – Superstructure completed.
- Block Work – 23rd -24th Floor in progress
- Conduiting – 22nd -23rd Floor in progress
- Gypsum – 22nd -23rd Floor in progress
- Balcony Tiling : 4th Floor in Progress
- Toilet Tiling : 9th Floor in Progress
- IPS Flooring : 8th Floor in Progress
Tower-B
- Structure – Superstructure completed.
- Block Work – 24th -25th Floor in progress
- Conduiting – 15th-16h Floor in progress
- Gypsum – 12th-13th Floor in progress
- Balcony Tiling : 4th Floor in Progress
- Toilet Tiling : 8th Floor in Progress
- IPS Flooring : 8th Floor in Progress
Tower-C
- Structure – Superstructure completed.
- Block Work – 31st-32nd Floor in progress
- Conduiting – 28th-29th Floor in progress
- Gypsum – 30th -31st Floor in progress
- Balcony Tiling : 3rd Floor in Progress
- Toilet Tiling : 13th Floor in Progress
- IPS Flooring : 10th Floor in Progress
Club
- Banquet & Reception : Terrace Slab in Progress
- Refreshment Area : Wall Stone Cladding & False Ceiling Framing in Progress
- Convenient Shop : Wall Gypsum is done
- Children Play Area : Wall Gypsum is done
- GYM & YOGA Room: Wall Stone Cladding in progress
- MALE SPA : Panelling frame in progress
Basement
- VDF for Parking in Progress
- STP & Water Tank in Progress
- Pump Room in Progress
- Ventilation Ducting in Progress
- Backfilling for landscaping in progress
Boundary Wall
- Compound wall with around 305 m casted and in progress